When it comes to upgrading or installing an air conditioning system, electrical work is not something to take lightly. Unfortunately, many homeowners fall into the trap of hiring a non-qualified electrician or attempting a DIY job, only to face expensive problems down the line. In this post, we’ll cover the National Electrical Code (NEC) requirements for installing a 60-amp fuse for your air conditioning system and highlight a real-world case where improper installation caused a fuse to blow.
Recently, we were called to a home where the air conditioning unit kept blowing fuses. After a thorough inspection, we discovered that a non-qualified electrician had worked on the system and miscalculated the required fuse size and wiring. This led to repeated fuse failures, which not only caused inconvenience but also posed a potential safety hazard.
We were able to fix the issue by following NEC guidelines and ensuring the installation was done correctly. Here’s a breakdown of the NEC codes we followed and why they matter.
The air conditioning unit in question was a Lennox 13ACC-060-230-01. The nameplate showed:
Based on this information, here’s how we corrected the installation, ensuring it complied with the NEC.
NEC 440 sets out the requirements for air conditioning systems. Here’s what we did:
MCA and MOP: The previous electrician failed to size the conductors properly, which caused the fuse to blow under load. Per NEC 440.32, the conductors must be sized to meet the MCA of 38 amps. We installed #8 AWG copper conductors (with a 75°C insulation rating) to handle the load safely.
Breaker or Fuse Size: The electrician used a fuse that didn’t match the unit’s MOP of 60 amps, leading to repeated failures. According to NEC 440.22(A), the fuse size must not exceed the MOP, so we installed the correct 60-amp fuse to provide proper protection.
Location of Disconnect: As required by NEC 440.14, we checked that the disconnect was installed correctly and was accessible for safety and serviceability.
NEC 240 governs overcurrent protection for electrical circuits. Here’s what went wrong:
NEC 310 covers conductor sizing.
Proper grounding is essential to prevent electrical hazards. We found that the system wasn’t properly grounded, which could have led to dangerous electrical faults.
NEC 110 covers general requirements for installation and electrical connections.
If the conductors were installed underground, they would need to meet the requirements of NEC 300.5. Luckily, this installation didn’t require that, but we checked the route of the conductors to ensure everything was compliant and well-protected.
Once we corrected the wiring, installed the correct 60-amp fuse, and ensured proper grounding, the system worked flawlessly. The homeowners were relieved to have a functioning air conditioning system just in time for the summer heat, without the constant worry of blown fuses.
This situation perfectly illustrates why it’s crucial to hire a qualified, licensed electrician when dealing with electrical systems—especially when it involves complex installations like air conditioning units. The homeowner had initially saved money by hiring a non-qualified electrician, but the repeated fuse failures ended up costing them more in the long run.
At Eco Solar and Electric, we ensure all work is done according to the NEC to prevent safety hazards and provide you with peace of mind. If you’re facing similar issues or need a system installed correctly the first time, give us a call. 714-786-5816 office 323-928-8880 Mobile
We’re here to help with all your electrical needs, ensuring safe and efficient installations every time.